11 Apr 2015 | |
GVK Power & Infrastructure Ltd has informed BSE that the 330MW (4x82.50MW) Alaknanda Hydro Power Company Limited, a step down subsidiary of the Company has successfully synchronised its First Unit of 82.50 MW with the grid on April 10, 2015 and is generating at full load.<BR><BR>The synchronisation of Second and Third Units with the grid are expected during this month and the last Unit (Fourth) is likely to be commissioned by next month. | |