RELIANCE POWER LTD. - Boiler Lightup achieved for fifth 660 MW Unit of 3,960 MW Sasan Ultra Mega Power Plant
Download announcement < Back
15 Jul 2014
Reliance Power Ltd has informed BSE that Boiler Light up has been achieved in respect of the Fifth 660MW unit of the 3,960 MW (6X660 MW) Sasan Ultra Mega Power Plant (UMPP) being developed by Sasan Power Limited, a wholly owned subsidiary of the Company.&lt;br/&gt;&lt;br/&gt;In this regard, the Company has issued a Media Release dated July 15, 2014 titled &quot;Boiler Lightup achieved for fifth 660 MW Unit of 3,960 MW Sasan Ultra Mega Power Plant&quot;.
View all announcements for RELIANCE POWER LTD. Source: BSE India