431 Infra Projects Hit by Rs 4.80 Lakh Cr Cost Overrun: MoSPI

By By Rediff Money Desk, NEWDELHI
Feb 25, 2024 10:25
MoSPI reports 431 infrastructure projects with cost overruns exceeding Rs 4.80 lakh crore in January 2024, impacting project completion timelines.
New Delhi, Feb 25 (PTI) As many as 431 infrastructure projects, each entailing an investment of Rs 150 crore or above, were hit by cost overrun of more than Rs 4.80 lakh crore in January 2024, an official report stated.

According to Ministry of Statistics and Programme Implementation (MoSPI), which monitors infrastructure projects worth Rs 150 crore and above, out of 1,821 projects, 431 reported cost overrun and 780 projects were delayed.

" Total original cost of implementation of the 1,821 projects was Rs 26,09,679.38 crore and their anticipated completion cost is likely to be Rs 30,90,135.99 crore, which reflects overall cost overruns of Rs 4,80,456.61 crore (18.41 per cent of original cost)," the ministry's latest report for January 2024 said.

According to the report, the expenditure incurred on these projects till January 2024 is Rs 16,43,821.69 crore, which is 53.20 per cent of the anticipated cost of the projects.

However, it stated that the number of delayed projects decreases to 583 if delay is calculated on the basis of the latest schedule of completion.

Further, it said that for 373 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Out of the 780 delayed projects, 194 have overall delays in the range of 1-12 months, 187 have been delayed for 13-24 months, 284 projects for 25-60 months, and 115 projects have been delayed for more than 60 months. The average time overrun in these projects is 36.13 months.

Reasons for time overrun, as reported by various project implementing agencies, include delay in land acquisition, in obtaining forest and environment clearances, and lack of infrastructure support and linkages. Delays in tie-up for project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, and law and order problems are among the other reasons.

The report also cited state-wise lockdowns due to COVID-19 (imposed in 2020 and 2021) as a reason for the delay in implementation of these projects.

It has also been observed that project executing agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported, it added.
Read More On:
infrastructure projectscost overrunmospiproject delayindia infrastructure
DISCLAIMER - This article is from a syndicated feed. The original source is responsible for accuracy, views & content ownership. Views expressed may not reflect those of rediff.com India Limited.

You May Like To Read

MORE NEWS

Punjab Seeks Korean Investment: Mann Visits Seoul

Punjab CM Mann urges Korean investment in Seoul, highlighting industry-friendly...

India-EU FTA Talks with Goyal: Key Issues &...

EU team meets Piyush Goyal to discuss India-EU Free Trade Agreement. Focus on steel,...

AI/ML in Power Distribution: Manohar Lal Keynote

Manohar Lal highlights AI/ML role in power distribution at national conference. Focus...

UIDAI Aadhaar Verification: New Rules & App

UIDAI to mandate registration for Aadhaar verification. New app & rules discourage...

Gold Price Outlook: Fed Decision & Rupee Impact

Gold prices to watch Fed meeting, rupee movement. Analysts predict potential gains amid...

Paint Makers Expect Q3 Uptick, Margin Improvement

Paint makers anticipate sales & volume growth in Q3 with improved margins due to benign...

Urban Vault Leases to Japanese Firms in Bengaluru

Urban Vault leases 21,000 sq ft office space in Bengaluru to Nachi, Pioneer, & Komatsu....

Dwarka Expressway Housing Prices Surge 3.5x in...

Dwarka Expressway property prices jumped 3.5 times in 5 years! Report by Square Yards...

Govt to Convert 40 GW Renewable Energy to FDRE:...

Suzlon expects the government to convert 40 GW of uncontracted renewable energy to...

Ola Electric Delivers 4680 Bharat Cell EVs

Ola Electric starts mass deliveries of 4680 Bharat Cell powered S1 Pro+ scooters....

Read More »

Sectoral Indices Market Indicators Listed Companies Gainers Losers Mutual Funds Portfolio Watchlist
© 2025 Rediff.com