Infrastructure Projects Hit by Rs 5.71 Lakh Cr Cost Overrun
Jun 23, 2024 11:02
458 infrastructure projects in India faced cost overruns totaling Rs 5.71 lakh crore in May 2024, according to MoSPI. Delays were also reported for 831 projects.
Illustration: Dominic Xavier/Rediff.com
New Delhi, Jun 23 (PTI) As many as 458 infrastructure projects, each entailing an investment of Rs 150 crore or above, were hit by a cost overrun of more than Rs 5.71 lakh crore in May this year, according to an official report.
According to the Ministry of Statistics and Programme Implementation (MoSPI), which monitors infrastructure projects worth Rs 150 crore and above, out of 1,817 projects, 458 reported cost overruns and 831 projects were delayed.
The total original cost of implementation of 1,817 projects was Rs 27,58,567.23 crore, and their anticipated completion cost is likely to be Rs 33,29,647.99 crore, which reflects an overall cost overrun of over Rs 5,71,080.76 (20.70 per cent of original cost), the ministry's latest report for May 2024 showed.
According to the report, the expenditure incurred on these projects till May 2024 is Rs 1,707,190.15 crore, which is 51.3 per cent of the anticipated cost of the projects.
However, the number of delayed projects decreased to 554, provided the delay is calculated on the basis of the latest schedule of completion, it added.
Of the 831 delayed projects, 245 have overall delays in the range of 1-12 months, 188 have been delayed for 13-24 months, 271 projects for 25-60 months, and 127 projects for more than 60 months.
The average time overrun in these 831 delayed projects is 35.1 months.
Reasons for time overrun, as reported by various project implementing agencies, include land acquisition, environmental clearance, financial issues, contractual/internal issues, manpower shortage and litigation issues.
Home »
Market News » Infrastructure Projects Hit by Rs 5.71 Lakh Cr Cost Overrun
DISCLAIMER - This article is from a syndicated feed. The original source is responsible for accuracy, views & content ownership. Views expressed may not reflect those of rediff.com India Limited.
You May Like To Read
MORE NEWS
Unilever: India Growth & GST Impact
Unilever sees huge opportunities in India due to high GDP growth and GST cuts. HUL...
Trai Recommends 6 GHz, E, V Band Allocation
Trai suggests administrative allocation of 6 GHz, E, and V bands for telecom backhaul....
TotalEnergies Sells Stake in Adani Green Energy
TotalEnergies sells 1.74% stake in Adani Green Energy for Rs 2,778 cr. Stake reduced to...
TCS Acquires Coastal Cloud for $700 Million
TCS acquires Coastal Cloud for USD 700 million, strengthening its Salesforce and AI...
JSW Paints Acquires AkzoNobel India Stake
JSW Paints completes acquisition of majority stake in AkzoNobel India, becoming the...
Park Medi World IPO Subscribed 52% on Day 1
Park Medi World''s IPO received 52% subscription on day 1. The Rs 920-crore IPO closes...
Dasnac Invests Rs 2,000 Cr in Noida Luxury Housing
Dasnac to invest Rs 2,000 crore in a luxury housing project, Dasnac Westminster, in...
Nephrocare IPO Subscribed 12% on Day 1
Nephrocare Health Services IPO received 12% subscription on day 1. IPO details, price...
Wakefit IPO Subscribed Over 2 Times
Wakefit''s Rs 1,289-cr IPO was subscribed over 2 times on the final day. Details on...
IAN Group to Deploy USD 100M Alpha Fund by 2027
IAN Group to deploy its USD 100 million IAN Alpha Fund in early-stage startups by 2027....
Read More »