Noida Airport Phase 1 Development: Rs 10,056 Crore Spent
Jan 29, 2024 22:00
Noida International Airport's first phase development is underway with over 70% of the Rs 10,056 crore budget already spent. The airport is expected to be operational by September 2024.
Photograph: PTI Photo
Noida, Jan 29 (PTI) The first phase of development of the upcoming international airport in Noida will cost Rs 10,056 crore and so far, around Rs 7,100 crore has already been spent on it, officials said.
S P Goyal, Additional Chief Secretary to Uttar Pradesh Chief Minister, on Monday reviewed the progress of the international airport in Jewar and directed officials concerned to ensure completion of work by September this year.
The first phase of the airport, being developed in 1,300 hectares, is scheduled to open for flight operations by September.
Goyal held a review meeting with officials of developer Yamuna International Airport Private Limited (YIAPL), a fully-owned subsidiary of Zurich International Airport AG, the concessionaire for the greenfield airport.
Kumar Harsh, Director, UP Civil Aviation; Noida Airport's Chief Operations Officer Kiran Jain; OSD Shailendra Bhatia; and Deputy Collector Abhay Singh were present in the meeting, according to a statement.
"During the review, the additional chief secretary was informed by YIAPL that the work of terminal building, ATC tower and runway is in progress by EPC contractor Tata Projects as per the development plan for the airport," the statement said.
"The concessionaire informed him that machinery and workforce have been increased at the airport site and the construction of the airport will be completed on time. He directed the officials that the development of the airport should be completed on time as per the milestone by September 2024," it added.
OSD Bhatia told PTI that an expenditure of Rs 10,056 crore will be incurred in the development of the first phase of the airport.
"Of this, expenditures worth around Rs 7,100 crore have been done till now, or over 70 per cent financial expenditures have been completed, which includes land acquisition and development," said Bhatia, who is also the additional CEO of the Yamuna Expressway Authority.
In its first phase, the airport which has been given code DXN, will have one runway, a terminal building with a capacity to handle 12 million passengers annually, according to officials.
Home »
Market News » Noida Airport Phase 1 Development: Rs 10,056 Crore Spent
DISCLAIMER - This article is from a syndicated feed. The original source is responsible for accuracy, views & content ownership. Views expressed may not reflect those of rediff.com India Limited.
You May Like To Read
MORE NEWS
ICICI Prudential AMC IPO Opens Friday
ICICI Prudential AMC raises Rs 3,022 Cr from anchor investors. IPO opens Dec 12. Price...
AWS Invests $7B in Telangana Data Center Expansion
AWS to invest USD 7 billion in Telangana for data center expansion over 14 years. Boost...
Cyber Attacks Surge Post Operation Sindoor
Cyber attacks on government networks surged 7x after Operation Sindoor. NICSI MD...
RBI Injects Liquidity via OMO Purchase
RBI injects Rs 50,000 crore liquidity through Open Market Operation (OMO) purchases of...
IndiGo Flight Disruptions: Captain Gopinath...
Captain Gopinath analyzes IndiGo flight disruptions, citing arrogance, poor planning,...
Leverage Edu: Dubai Study Surge from India
Leverage Edu reports a 40x surge in applications from India to study in Dubai. Dubai is...
RBI Cancels NBFC Registrations
RBI cancels registration of 4 NBFCs, 4 others surrender certificates. Action taken...
RBI Eases Cash Credit Restrictions
RBI relaxes restrictions on cash credit facilities after stakeholder feedback. Draft...
Indian Startup Funding & Investments News
Latest funding news: Neosapien raises USD 2 mn, Isprout borrows Rs 60 cr, Ekta World...
Rajasthan Progressing: CM Sharma on Development
CM Sharma highlights Rajasthan's rapid progress in tourism, IT, renewable energy,...
Read More »