Silkyara Tunnel Collapse: Govt to Revamp Tunnel Construction SOPs
Jan 05, 2024 18:17
The Indian government will revamp tunnel construction SOPs after an expert panel found shortcomings in the Silkyara tunnel collapse, which stranded 41 workers. The project will not be abandoned.
Photograph: PTI Photo
New Delhi, Jan 5 (PTI) The government on Friday said it will revamp the standard operating procedures for tunnel construction after an expert panel found many shortcomings in the under-construction Silkyara tunnel, which collapsed in November last year, leaving 41 workers stranded for more than two weeks.
At a press briefing, Road Transport and Highways Secretary Anurag Jain said the Silkyara tunnel project in Uttarkashi is still workable, and the government will not abandon it.
An experts' panel to investigate the collapse of a portion of the under-construction Silkyara tunnel has pointed out many shortcomings in the project, he added.
"Silkyara tunnel collapse se humne kaafi kuch seekha hai (We have learnt a lot from the collapse of the under-construction Silkyara tunnel)," he said.
A total of 41 workers were trapped after a portion of the under-construction tunnel collapsed on November 12 and the workers were rescued on November 28.
The Ministry of Road Transport and Highways (MoRTH), on December 6, constituted a five-member committee to investigate the collapse of the tunnel.
"The committee has suggested some changes in standard operating procedures (SOPs) of tunnel construction. Based on the committee's suggestion, we will change SOPs for tunnel construction to prevent the occurrence of Silkayara-like mishaps in the future," he added.
The National Highways and Infrastructure Development Corporation Ltd (NHIDCL) is constructing the Silkyara-Barkot tunnel through Hyderabad-based Navayuga Engineering Company Ltd.
The tunnel is a single-tube tunnel divided into two inter-connected corridors by a partition wall. Each inter-connector corridor can work as an escape passage for the other.
The 4.5 kilometre-long tunnel project in Uttarakhand, which is part of the centre's 900 kilometre-Char Dham Yatra all-weather road, aims to improve connectivity to the four pilgrimage sites.
Home »
Market News » Silkyara Tunnel Collapse: Govt to Revamp Tunnel Construction SOPs
DISCLAIMER - This article is from a syndicated feed. The original source is responsible for accuracy, views & content ownership. Views expressed may not reflect those of rediff.com India Limited.
You May Like To Read
MORE NEWS
DRI Seizes Red Sanders Worth Rs 6.26 Cr, 4...
DRI seizes 15 MT of red sanders worth Rs 6.26 crore in Delhi, arrests 4. Illegal export...
UAE Fund to Invest ₹1,000 Cr in Kerala Startups
UAE-based Feeder Fund to invest ₹1,000 crore in Kerala startups over 3 years. Boost...
ECL Aims for 58 MT Output, Mine Closures Planned
Eastern Coalfields Ltd (ECL) targets 58 MT output, plans closure of six underground...
India: Export Potential in Russia
300 Indian products have huge export potential in Russia. Engineering, pharma, agri,...
Gold & Silver Rally: Inflation Data in Focus
Gold and silver prices rally amid inflation data focus. Analysts eye central bank...
India Ranks 3rd in Global AI Vibrancy Index
India ranks 3rd in Stanford University's Global AI Vibrancy tool, surpassing advanced...
EPFOA Urges CPFC: Equip Offices for Compliance
EPFOA urges CPFC to equip field offices with authority & tools to handle default &...
TV Prices to Rise in January: Chip Shortage &...
TV prices are expected to increase in January due to memory chip shortages and a...
India Gems & Jewellery Exports Up 20% in November
India's gems and jewellery exports grew 20% to USD 2.5 billion in November, says GJEPC....
Navi Mumbai Airport: 3rd Runway Feasibility Study
CIDCO invites bids for a consultant to study the feasibility of a third runway at Navi...
Read More »