BHEL Commissions Punatsangchhu-II Hydroelectric Project in Bhutan
Bharat Heavy Electricals Limited (BHEL) has successfully commissioned two units of the 6x170 MW Punatsangchhu-II Hydroelectric Project (PHEP-II) in Bhutan, boosting power generation in the region.

Haridwar, Jan 8 (PTI) Bharat Heavy Electricals Limited has successfully commissioned two units of the 6x170 MW Punatsangchhu-II Hydroelectric Project (PHEP-II) in Bhutan.
Executed as part of a bilateral agreement between the Indian and Bhutanese governments, PHEP-II is a greenfield hydro project located in the Wangdue district of Western Bhutan, a BHEL press release said.
Significantly, the Francis Turbine installed in the project is designed to operate at a rated head of 241 metres the highest for any Francis Type Hydro Turbine in Bhutan.
On commissioning of all six units, the expected annual power generation will be 4,357 gigawatt-hours, the release said.
Unit 1 and 2 of the 6x170 MW PHEP-II were synchronised on December 16 and 17, 2024, respectively.
Executed as part of a bilateral agreement between the Indian and Bhutanese governments, PHEP-II is a greenfield hydro project located in the Wangdue district of Western Bhutan, a BHEL press release said.
Significantly, the Francis Turbine installed in the project is designed to operate at a rated head of 241 metres the highest for any Francis Type Hydro Turbine in Bhutan.
On commissioning of all six units, the expected annual power generation will be 4,357 gigawatt-hours, the release said.
Unit 1 and 2 of the 6x170 MW PHEP-II were synchronised on December 16 and 17, 2024, respectively.
You May Like To Read
TODAY'S MOST TRADED COMPANIES
- Company Name
- Price
- Volume
- Vodafone Idea L
- 10.37 (+ 1.27)
- 92075867
- Billionbrains Garage
- 130.94 (+ 30.94)
- 62442302
- Spright Agro
- 0.61 ( -4.69)
- 48391729
- Sunshine Capital
- 0.27 ( -3.57)
- 48124515
- Murae Organisor
- 0.31 (+ 3.33)
- 25320519