NHPC's Parbati-II Project Boosts Himachal Revenue
x
NHPC's Parbati-II hydroelectric project in Himachal Pradesh is set to increase annual revenue by Rs 224.70 crore after it begins operations. Read more.
New Delhi, Apr 24 (PTI) State-owned hydro power giant NHPC on Thursday said the annul revenue of its 520-MW ParbatiIII Power Station will increase by Rs 224.70 crore, once the 800-MW Parbati-II project in Himachal Pradesh begins operations.
The power generation at 520-MW Parbati-III power station will increase to 1,669 million units (MUs) in 2025-26 from 572 MUs recorded in 2024-25, NHPC said in a regulatory filing.
Accordingly, with operationalisation of Parbati-II hydro electric project (4X200 MW) Himachal Pradesh, the revenue of Parbati-III Power Station will increase by Rs 224.70 crore to Rs 425.20 crore in 2025-26 from Rs 200.50 crore in 2024-25.
The 520-MW station is situated on the downstream of the Parbati-II Project Power House.
Prabat-II power station has begun commercial supplies recently.
Parbati Hydroelectric Project (Stage-II) is a run-of-the-river scheme proposed to harness hydro electricity potential of the lower reaches of the river Parbati.
The river is proposed to be diverted with a Concrete Gravity Dam at Village Pulga in Parbati valley through a 31.52-km Head Race Tunnel (HRT) and the power house shall be located at village Suind in Sainj valley.
Thus gross head of 863 m between Pulga and Suind will be utilised for generating 800 MW of electricity.
Parbati-III power station, commissioned in 2014, is a pondage type scheme, providing peaking support to the grid to make use of the hydropower potential of river Parbati, Manihar Nallah, Panch Nallah, Huria Nallah & Jiwa Nallah via Parbati-II hydro electric Project and Sainj River.
The power generation at 520-MW Parbati-III power station will increase to 1,669 million units (MUs) in 2025-26 from 572 MUs recorded in 2024-25, NHPC said in a regulatory filing.
Accordingly, with operationalisation of Parbati-II hydro electric project (4X200 MW) Himachal Pradesh, the revenue of Parbati-III Power Station will increase by Rs 224.70 crore to Rs 425.20 crore in 2025-26 from Rs 200.50 crore in 2024-25.
The 520-MW station is situated on the downstream of the Parbati-II Project Power House.
Prabat-II power station has begun commercial supplies recently.
Parbati Hydroelectric Project (Stage-II) is a run-of-the-river scheme proposed to harness hydro electricity potential of the lower reaches of the river Parbati.
The river is proposed to be diverted with a Concrete Gravity Dam at Village Pulga in Parbati valley through a 31.52-km Head Race Tunnel (HRT) and the power house shall be located at village Suind in Sainj valley.
Thus gross head of 863 m between Pulga and Suind will be utilised for generating 800 MW of electricity.
Parbati-III power station, commissioned in 2014, is a pondage type scheme, providing peaking support to the grid to make use of the hydropower potential of river Parbati, Manihar Nallah, Panch Nallah, Huria Nallah & Jiwa Nallah via Parbati-II hydro electric Project and Sainj River.
You May Like To Read
TODAY'S MOST TRADED COMPANIES
- Company Name
- Price
- Volume
- Spright Agro
- 0.70 (+ 4.48)
- 110120075
- Vodafone Idea L
- 9.61 (+ 3.67)
- 84379834
- Murae Organisor
- 0.28 (+ 3.70)
- 35538309
- Sunshine Capital
- 0.28 (+ 3.70)
- 26912524
- Suzlon Energy Ltd.
- 57.39 ( -3.76)
- 14790944