Subansiri Lower Unit-2 to Start Commercial Supply

1 Minute Read Listen to Article
Share:    

Dec 03, 2025 14:55

x
NHPC announces Subansiri Lower hydro project's 250 MW Unit-2 is expected to begin commercial supply in December 2025. Test synchronisation achieved.
Subansiri Lower Unit-2 to Start Commercial Supply
Photograph: Amit Dave / Reuters.
New Delhi, Dec 3 (PTI) State-owned hydro power giant NHPC on Wednesday said that 250 MW Unit-2 of Subansiri Lower hydro project is expected to begin commercial supply this month.

According to a regulatory filing, test synchronisation of the 250 MW (Unit-2) of 2000 MW of Subansiri Lower hydro-electric Project with the national grid has been successfully achieved on December 2, 2025 (evening).

The Commercial Operation (CoD) of Unit-2 is expected in the month of December 2025, it stated.


Subansiri Lower is a run-of-river scheme with small Pondage on the river Subansiri.

The Project is located near North Lakhimpur on the border of Arunachal Pradesh and Assam. The nearest railhead is Gogamukh/North Lakhimpur and the nearest airport is Lilabari / Dibrugarh.

The estimated annual energy generation from the Project is 7421.59 MU in a 90 per cent dependable year.
Share:    

TODAY'S MOST TRADED COMPANIES

  • Company Name
  • Price
  • Volume

See More >

Moneywiz Live!

Home

Market News

Latest News

International Markets

Economy

Industries

Mutual Fund News

IPO News

Search News

My Portfolio

My Watchlist

Gainers

Losers

Sectors

Indices

Forex

Mutual Funds

Feedback